Challenge Bode Gravel Companys new facility was to be located on Portproperty in an industrial community with poor ground conditions. Extensive environmental compliance requirements as well as space and height restrictions were specified. Pre-engineered equipment for the Central Mix Plant and Dry Batch Plant were to be incorporated into the design. It was a requirement to increase production and efficiency by 20%. Additionally, Bode Gravel also wanted the facility to enhance the neighboring community, and not look like a typical concrete batch plant. Solution The design-build team worked closely with City, Port,
and County planning departments to design a unique plant configuration
only two-thirds the height of the former. 156 piles were driven to overcome
the bay mud ground conditions. State-of-the-art dust Highlights
|
||
|
|
|||